OUR PROJECT

Chichester Solar Farm

PROJECT DURATION

20 Months

PROJECT EQUIPMENT

20+

PERSONNEL SUPPLIED

30+

Project Overview

The Chichester Solar Farm supports the power infrastructure for Fortescue Metals Group Christmas Creek and Cloudbreak mining operations and the neighbouring Roy Hill mine. Maramara was engaged to undertake the civil works for the new solar farm, working across multiple mine sites and adhering to the stakeholders’ protocols.

Project Scope

 Construction of rail siding
 Clearing ~140 hectares
  Construction of all roads & substation benches, across 3 mine sites
  70,000 sqm of hardstand for the panel installation
  Preparation of transmission line pads